Development tracker Locator map: Solano Daily, using 2023 U.S. Census Bureau municipal boundaries. Under construction · Suisun City
Location not published in city update
97 affordable apartments. The city reported in May 2026 that construction had officially started. Completion date not announced.
Locator map: Solano Daily, using 2023 U.S. Census Bureau municipal boundaries. Approved, not yet under construction · Suisun City
Main St.
20-unit apartment building on Main Street approved in August 2025. Completion date not announced.
Locator map: Solano Daily, using 2023 U.S. Census Bureau municipal boundaries. Under construction · Suisun City
97 Sunset Center
New Dutch Bros Coffee drive-through. The city said in its June 2026 newsletter that construction had begun; in May it had said the project was nearing building-permit issuance. The company's location page still listed the shop as coming soon on Nov. 13, 2026. Opening date not announced.
Locator map: Solano Daily, using 2023 U.S. Census Bureau municipal boundaries. Approved, not yet under construction · Suisun City
South of Hwy. 12 at Pennsylvania Ave.
About 1.28 million sq ft of warehouse and logistics space. City Council adopted the zoning and planned-unit-development ordinances on Dec. 3, 2024. Construction start and completion dates not announced. The developer is Buzz Oates Construction, which filed its application in 2021. The project needs land annexed into Suisun City, so the Solano Local Agency Formation Commission also has to sign off. The council's first vote, in November 2024, was 4-1, with then-Vice Mayor Princess Washington voting no, the Daily Republic reported. The council adopted the ordinance on Dec. 3, 2024, on a 5-0 vote, according to the city's notice of adoption. The two records describe the project's size differently. The city's notice describes a 1.28 million-square-foot warehouse and logistics project. The Daily Republic's report on the first vote described 529,708 square feet on 53 acres, with the rest of the land kept as managed open space, and said the Planning Commission had recommended the original 1.28 million. Solano Daily has not reconciled the two. The project as the Daily Republic described it was expected to bring the city's general fund more than $1.8 million in revenue against $635,000 in expenses. Steve Chappell of the Suisun Resource Conservation District told the council a similar plan was proposed in 2006 as the Gentry Project and abandoned, the newspaper reported.
Locator map: Solano Daily, using 2023 U.S. Census Bureau municipal boundaries. Under city review · Suisun City
Lotz Way
16-home neighborhood with accessory dwelling units, listed as entitled in the city's September 2025 calendar; in May 2026 the city said it was reviewing plans for the 16 townhomes. Completion date not announced.
Locator map: Solano Daily, using 2023 U.S. Census Bureau municipal boundaries. Approved, not yet under construction · Suisun City
McCoy Creek Rd.
31 apartments with commercial space. Listed as under review in the city's September 2025 calendar; by May 2026 the city said it was processing permits. Completion date not announced.
Locator map: Solano Daily, using 2023 U.S. Census Bureau municipal boundaries. Under city review · Suisun City
Off Olive Ave., south of E. Tabor Ave.
Proposed subdivision of about 70 single-family homes, under city review as of the September 2025 development calendar. Completion date not announced. The site is off Olive Avenue, just south of East Tabor Avenue. The applicant, Suisun Investments, describes a gated neighborhood of 70 single-family lots with a park and open space. This is a second try. The City Council approved an 80-lot map for the southern part of the site in 2010, but that approval ran out. The new plan adds a 2.75-acre parcel and still cuts the lot count to 70. The streets would be private and maintained by a homeowners association, which the applicant says would lower the city's upkeep costs. The developer held a neighborhood meeting on Feb. 28, 2024, at the Joseph Nelson Community Center.
Locator map: Solano Daily, using 2023 U.S. Census Bureau municipal boundaries. Under city review · Suisun City
22,873 acres of unincorporated land around Hwy. 12 and Hwy. 113 proposed for annexation
California Forever's proposal to annex 22,873 acres into Suisun City. The city's November 2025 environmental notice describes about 65,217 homes and 84,479 jobs in a 20-year plan on 6,080 acres, and about 173,913 homes and 225,471 jobs at full build-out on 15,737 acres. In environmental review; no approval or construction date. The City Council opened the door on June 10, 2025, voting 4-1 for an agreement that has California Forever pay for the city's staff time, consultants and environmental review. Councilmember Princess Washington cast the no vote. The company put down $400,000 and agreed to pay $10 million for public benefits if the annexation goes through: $3.5 million if the city presents an annexation plan and $6.5 million if the county's boundary commission approves it. Deputy City Manager Jim Bermudez laid out a schedule in May: a draft environmental report in fall 2026, certification by winter, approval hearings in spring 2027 and a decision by the Solano Local Agency Formation Commission in 2027 or 2028, the Vallejo Sun reported. The council is weighing only a first phase, the Sun reported; anything more would need a new environmental review. "Suisun City needs growth, it needs industry," City Manager Bret Prebula said, according to the Vallejo Sun's May 15, 2026 report. Opponents want a public vote. In April, the Solano Together coalition rallied outside City Hall and asked the council to put an advisory measure on the November 2026 ballot. The Nov. 3 election has not changed the city's direction, on the count so far. Mayor Alma Hernandez, who told KQED before the election that she would continue exploring annexation, led with 37.2% (3,242 votes) in results updated Nov. 13. Councilmember Amit Pal had 28% and Michael Jefferson 16.2%. Jefferson told KQED he planned, on his first day as mayor, to have two council allies vote with him to terminate the city's contract with California Forever. Results have not been certified. Solano Daily had not confirmed, as of Nov. 15, whether the draft environmental report has been released. The city's schedule called for it in fall 2026.
Locator map: Solano Daily, using 2023 U.S. Census Bureau municipal boundaries. Under city review · Suisun City
East of Walters Rd., south of Petersen Rd.
Proposed warehouse and distribution center in environmental review; a partially recirculated draft EIR was open for comment through Sept. 8, 2026. The city says this and the Highway 12 project together total nearly 3.4 million sq ft. Completion date not announced. Buzz Oates Construction proposes about 2.1 million square feet of warehouses in six buildings, the smallest at 145,397 square feet and the largest at 644,782. They would cover about 120 acres of a 167.43-acre site. The remaining 47 acres would be kept as open space. The land is grazing land in the unincorporated county, inside Suisun City's planning area, and all of it would be annexed. Travis Air Force Base is on its east side, Petersen Road on the north and Highway 12 on the south. Trucks and cars would enter at one point on Walters Road and three on Petersen Road. An earlier state filing estimated 2,843 jobs.